India’s bullet train goes live: First 50km stretch energised, trains awaited
India’s first bullet train project has achieved a major milestone with the successful energisation of the overhead electrical system on the approximately 50-km Surat–Bilimora section of the Mumbai–Ahmedabad High-Speed Rail Corridor on November 20, 2026, paving the way for further testing of the high-speed railway.
The electrification covers both Up and Down lines of the elevated corridor. Officials said energisation would be undertaken progressively in smaller sections under technical supervision to ensure safety and compliance with prescribed procedures.
The 508-km Mumbai–Ahmedabad Bullet Train corridor will operate on an advanced 2 × 25 kV overhead traction system designed for high-speed railway operations.

While the Surat–Bilimora section has now been electrified, the trains that will run on the route are still being built. The first Indian-made B28 bullet train, being manufactured by BEML in Bengaluru, is expected to be ready for dispatch by February 2027.
Each train will have eight coaches, carry around 557 passengers and run at speeds of up to 250 kmph. The project was originally planned with Japanese E5 Shinkansen trains capable of running at 320 kmph, but delays in getting these trains and the availability of the newer E10 model led to the decision to use Indian-made B28 trains for the initial services.
Trial runs have not yet begun, and the first passenger services are planned for August 2027, depending on testing and safety approvals.
Explaining about the electrification, officials said the electrical network will be supported by 14 traction substations (TSS) strategically located along the corridor. These will draw electricity from the national grid and supply power to the overhead equipment that will eventually operate the high-speed trains.
At Bilimora in Gujarat’s Navsari district, installation work has been completed in the control panel, changeover switch, transformer and circuit breaker buildings of the first traction substation. The Gujarat traction network will receive electricity from the 220 kV Ambetha Grid Substation of Gujarat Energy Transmission Corporation Limited (GETCO).
The entire electrical network will be monitored through a centralised control centre to ensure safe and reliable operations.
The Surat–Bilimora stretch comprises approximately 50 km of elevated alignment, including bridges across four rivers and a steel bridge over National Highway 53. Around 94,000 noise barriers have also been installed along the viaduct to minimise the impact of high-speed train operations on surrounding areas.
With the overhead electrical equipment now energised, project authorities have warned residents, commuters, construction workers and others against approaching or touching electrical installations or undertaking unauthorised work near the alignment.
The milestone marks an important transition from infrastructure construction towards systems testing on India’s first high-speed rail corridor, although energisation does not itself signify the commencement of train trials or passenger operations.
Energisation will be carried out progressively in smaller sections, under the close supervision of the technical teams to ensure safety and compliance with prescribed procedures.
The section comprises both Up and Down lines on the elevated alignment and marks an important advancement towards further testing activities for the project.
The Mumbai–Ahmedabad Bullet Train corridor is equipped with an advanced 2 × 25 kV Overhead Traction System, one of the sophisticated electrification technologies used for high-speed rail systems worldwide.
The electrification network comprises 14 strategically located Traction Substations (TSS) along the 508 km corridor. These substations will receive power from the National grid and supply it to the overhead traction system used by high-speed trains.
The first Traction Substation at Bilimora, in Navsari district of Gujarat, has completed installation works in the Control Panel, Changeover Switch, Transformer and Circuit Breaker buildings.
The TSS in Gujarat will receive power from the 220 kV Ambetha Grid Substation of Gujarat Energy Transmission Corporation Limited (GETCO).
The entire electrical network will be monitored through a centralised control centre to ensure safe and reliable operations.
The Surat–Bilimora section comprises approximately 50 km of elevated alignment between the two stations. The alignment includes bridges across four rivers and a steel bridge over National Highway 53 (NH-53). The viaduct is also equipped with approximately 94,000 noise barriers to minimise noise impact on the surrounding areas.