26-km Borivali–Virar 5th & 6th line project is being implemented by MRVC at cost of Rs 2,184 crore
Station-wise Ground Status as per MRVC (Dec 2025)
Borivali
- No remodelling required
- Existing slow lines continue
- New lines branch westward beyond station
Status: No major work inside station limits
Dahisar
- New platforms planned west side (slightly north)
- Retaining wall & earthwork started
- Dahisar Nalla Bridge 66: foundation work underway
Status: Foundations and earthwork in progress
Dahisar–Mira Road section
- Fastest-moving stretch of the project
- Forest clearance already obtained
- Heavy earthwork and formation advancing
Status: Leading section overall
Mira Road
- Two new platforms directly west of existing PF-1
- Station improvement & elevated deck works ongoing
Status: Initial platform and station works visible
Bhayandar
- One of two stations with major remodelling
- New west-side terminating platform planned
- Platform re-assignment for slow, fast, and new lines
- Elevated deck under construction
Status: Active remodelling and structural works
Bhayandar Creek
- Bridge 73 (North Basin Creek):
- Well foundations started
- Old historic bridge dismantling underway
Status: Foundation stage (time-critical structure)
Panju Island
- Clearing and grubbing underway
- No road access; contractor planning barge/ferry logistics
Status: Preparatory works in progress
Naigaon
- Bridge 75 (North Basin Creek): pile foundations started from north end
- Casting yard planned here for major creek bridges
- FOB extensions underway
Status: Foundations and earthwork progressing
Vasai Road
- Second station with major remodelling
- Platform 1 to shift ~8 m west
- New slow-line platforms planned west of PF-2
- Old road overbridge demolished; new ROB planned
Status: Demolition completed; remodelling preparation ongoing
Nalasopara
- New west-side home platform planned
- Existing PF-1 to become island platform
- Piling machines already deployed
Status: Foundation works underway
Virar
- One additional platform for new lines
- Further platforms planned under Virar–Dahanu project
Status: Planning stage; execution linked with adjoining projects
Overall Snapshot
- Earthwork and foundations advancing well
- Creek bridges (73 & 75) will decide timelines
- Limited land acquisition; relocations mainly at Vasai & Nalasopara
- Expected commissioning: End-2028 (possible earlier if bridge works stay on track)